TOKYO, Japan, November 21, 2024 – Honda Motor Co., Ltd. has unveiled the demonstration production line for all-solid-state batteries, which are being developed independently by Honda for mass production at the site located at Honda R&D Co., Ltd. In Sakura City, Tochigi Prefecture, Japan.
When conducting technical verification to establish a mass production process on the demonstration line, Honda will determine the basic specifications of the battery cells, with an aim to begin applying its all-solid-state batteries to the electrified models introduced to market in the second half of the 2020s.Honda built the demonstration line to replicate the processes required for mass production. It has a total floor area of approximately 27,400 m2 (295,000 ft2) and is equipped with facilities and equipment that enable verification of each production process. This includes weighing and mixing of electrode materials, coating and roll pressing of electrode assembly and the formation of cells, and assembly of the module.
The construction of the facility was completed in the spring, with almost all key equipment necessary for verification now installed. Honda is planning to begin battery production on this demonstration line in January 2025 and will conduct verification of mass production technologies and costs for each process, while also developing battery cell specifications.
By increasing cost competitiveness of its all-solid-state batteries through the adoption of a highly efficient production process and by expanding application of the batteries to a wide range of Honda mobility products, including automobiles, motorcycles and aircraft, Honda aims to further reduce battery costs via economies of scale and expand the joy of mobility.
Keiji Otsu, President and Representative Director of Honda R&D Co., Ltd.: “The all-solid-state battery is an innovative technology that will be a game changer in this EV era. Replacing engines that have been supporting the advancements of automobiles to date, batteries will be the key factor of electrification. We believe that advancement of batteries will be a driving force in the transformation of Honda.
“Now, the start of operation of our demonstration production line for our all-solid-state batteries is in sight, and we can say that we have reached an important milestone for Honda and the country of Japan. We will continue taking on challenges to launch our mobility products equipped with our all-solid-state batteries as quickly as possible so that Honda can offer new value to our customers.”
For more technical information, visit: https://global.honda/en/newsroom/news/2024/c241121eng.html
About the demonstration production line for all-solid-state batteries
Location |
Sakura City, Tochigi Prefecture, Japan |
Lot size |
Approximately 12,900 m2 (139,000 ft2) |
Total floor area |
Approximately 27,400 m2 (295,000 ft2) |
Investment amount |
Approximately 43 billion yen |
Note: This demonstration line is partially funded by a grant from the Green Innovation Fund of the New Energy and Industrial Technology Development Organization (NEDO) of Japan.